The Miller Act[1] requires any general contractor awarded a federal government contract for more than $100,000 to secure two bonds: a performance bond to protect the government and a payment bond “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract.”[2] The purpose of the Miller Act is to ensure payment to these subcontractors that the prime contractor fails to pay. A subcontractor working on a project for which a payment bond is issued may bring suit if it has not been paid in full within 90 days of completing its work, and may collect judgment on the bond for the amount due.[3]
The Miller Act provides an exclusive federal cause of action for subcontractors to recover from a prime contractor’s insurer in the event that the prime contractor fails to pay the subcontractor. The statute allows wavier of that right if the waiver is: (1) in writing; (2) signed by the person whose right is waived; and (3) executed after the person whose rights are waived has furnished labor or material for use in the performance of the contract.[4] Courts have held that a waiver of the Miller Act right of action may only be made in “clear and explicit” terms.[5]
Clarifying the Act
In U.S. ex rel. McKenney’s Inc. v. Government Technical Services,[6] a Federal District Court in Georgia was confronted with a conflict between the Miller Act policy concerns favoring payment to subcontractors and suppliers and the clear meaning of a pay-when-paid clause. The dilemma confronted by the Court in the McKenney case was that if the government was to delay paying for more than a year, and the pay-when-paid clause was to be enforced, the one-year Miller Act statute of limitations would expire, thus denying the availability of a Miller Act action to the subcontractor. The court refused to interpret the interruption between the pay-when-paid clauses and the Miller Act in a way that would frustrate the remedial nature of the Miller Act. The court declined to turn a pay-when-paid contract provision into an implicit waiver of the subcontractor’s Miller Act rights.[7]
In U.S. ex rel. A&R Supply of Mississippi v. Travelers Casualty & Surety Co.,[8] the surety asserted an estoppel defense to the subcontractor’s payment bond claim. While estoppel is a proper defense to a Miller Act claim, a party asserting an estoppel defense must show that it was misled to its detriment. The surety alleged that the sub-subcontractor misled the general contractor into believing that the sub-subcontractor would retain payment from the general contractor through the creation of a joint check agreement. The surety asserted that since the subcontractor prepared a joint check agreement, the sub-subcontractor assured the general contract that it would be paid.
However, the Court held that a request for a joint payment procedure did not constitute a waiver of Miller Act rights, but was actually a request for and acceptance of additional security. Thus, the sub-subcontractor’s endorsement of joint checks was not a representation by the sub-subcontractor that it had been paid. Critically, a request for a joint payment procedure will only limit Miller Act rights if it includes a “clear expression of an intent to waive the protection afforded by the Miller Act.”[9]
The Ninth Circuit has held that a pay-when-paid clause generally may not be relied upon by a Miller Act surety to excuse payment. Under the Miller Act, the surety’s liability is not measured by the liability of the contractor, but is instead determined exclusively by the Miller Act. A subcontractor can only waive the protections provided by the Miller Act if it has done so voluntarily, knowingly, clearly and explicitly; a difficult standard that is not satisfied by a pay-when-paid provision.[10]
When to Demand Payment
In Walton Technology, Inc. v. Westar Engineering, Inc., the subcontractor filed a lawsuit against a prime contractor and its surety under the Miller Act, claiming unjust enrichment and conversion based on the subcontractor’s belief that it was entitled to a pro rata portion of the prime contractor’s insurance recovery for rental fees. The prime contractor stated that with regard to the Miller Act claim it was not liable to the subcontractor because the pay-when-paid clause had not been satisfied. The court disagreed, holding that the clause did not constitute a “clear and explicit waiver of its Miller Act rights.”[11]
However, in Fixture Specialists, Inc. v. Global Construction, LLC,[12] the court held that if a condition precedent has not been satisfied pursuant to a valid pay-when-paid clause, a surety may use such clause as a defense against the subcontractor for demand of payment, because the prime contractor’s duty to pay has not accrued.
In Fixture, the subcontractor filed a lawsuit against a prime contractor and its surety under the Miller Act seeking payment for completion of work. The prime contractor stated that with regard to the Miller Act claim, it was not liable to the subcontractor because the pay-when-paid clause had not been satisfied. The court agreed holding that the language of the clause clearly and unambiguously created a condition precedent to any obligation of the prime contractor.[13]
[1] 40 U.S.C § 3131 et seq.
[2] 40 U .S.C. § 3131(b)
[3] Id § 3131(b). U.S. ex Rel. McKenney’s, Inc. v. Government Technical Services, LLC, 531 F. Supp. 2d 1375, 1376, 1377 (N.D. Ga. 2008).
[4] 40 U.S.C. § 3131(c)
[5] Lee & Rua Co. v. Great American Insurance Co., 2008 U.S. Dist. Lexis 36317 (W.D. Wa.); United States ex rel. Walton Tech., Inc. v. Weststar Eng’g Inc., 290 F.3d 1199, 1209 (9th Cir. 2002).
[6] 531 F. Supp 2d 1375 (N.D. Ga. 2008)
[7] U.S. ex reI. McKenney’s Inc., supra., 53I F. Supp. 2d at 1379, 1380.
[8] 2008 U.S. App. Lexis 2754, *5, 6, 7 (5th Cir. 2008)
[9] U.S. ex rel. A&R Supply of Mississippi, supra., at *5, 6.
[10] Walton Technology, Inc. v. Westar Engineering, Inc., 290 F.3d 1199 (9il Cir. 2002).
[11] Id. at 24.
[12] No. 075614,2009 WL 90403 I (D.N.J. March 30, 2009)
[13] Fixture Specialists, Inc., supra., at *6.
