The Relationships Shaping Modern IGUs
by Joshua Huff
Glass fabricators lean heavily on suppliers to cut costs, boost quality and accelerate the development of new processes and products. For that relationship to work, the two rely on a collaborative partnership that helps both evolve and meet changing needs. Rising performance demands in the glass fabrication industry are turning those relationships into technical partnerships.
That nuanced cooperation comes as fabricators pursue the development of insulating glass units (IGU) with greater seal durability, gas retention, edge performance, material compatibility and long-term thermal stability. And as IG systems become larger, fabricators and their suppliers are being pushed into earlier, deeper and more data-driven collaboration, says Derek Losee, sales manager for the German company sedak.
“The relationship has become much more collaborative and engineering-driven than it was in the past,” he explains. “Years ago, many component suppliers were treated primarily as material providers: a fabricator selected a spacer, sealant, coating or gas-fill system based on published specifications and incorporated it into a standard IGU process. That approach is not sufficient for oversized and complex IGs.”
Losee adds that as a result, the component supplier has become more than a vendor; they are part of the technical risk assessment. Fabricators must understand how a component performs not only in thermal isolation but within the complete IGU system: the real size, geometry, coating position, edge design, transport concept, installation method and long-term building exposure.
“It has moved from simple procurement toward early-stage engineering collaboration,” says Losee.
That shift is changing when conversations happen, what information is shared and who is involved before an IGU ever reaches production.
Early Input, Better IGUs
Kelly Isom, operations manager at Press Glass in Virginia, says in the best cases, fabricators and suppliers share production records, batch information, test data, installation conditions and field observations early in the process.
“As IGUs become larger, heavier and more performance-driven, fabricators rely more on suppliers for testing data, compatibility guidance, application engineering and long-term durability expertise,” he explains. “At the same time, suppliers depend on fabricators to validate how products actually perform in production and in the field.”
Isom adds that pressure to design buildings with higher thermal performance, tighter aesthetics and longer warranties has pushed architects and building owners to communicate earlier and work more closely than in the past.
This has become more important as IGUs have become larger, up to 50 or more feet long, says Losee. At those dimensions, small details become more consequential: edge seal design, spacer placement, coating deletion, cavity behavior, handling, support conditions and shipping loads.
Isom notes that the pressure to deliver a product that meets the specified conditions has several benefits, mainly higher quality requirements for components and a closer and more collaborative relationship with a stronger focus on quality, technical support and problem-solving.
“Today we’re seeing oversized glass, triple glazing, thicker laminates, structural silicone details, complex coatings and tighter visual quality expectations all combined into a single assembly,” says Isom. “Close collaboration becomes especially important in newer and more complex make-ups involving multi-layer laminates, structural silicone glazing, U-channels and cassette systems used in structural silicone glazing applications.”
Preventing Field Issues
Performance issues can still arise even with strong quality controls in place. Suppliers may design components around specific performance parameters, while fabricators account for real-world production tolerances, handling risks and project-specific requirements. If those expectations are not aligned, problems may not become visible until the unit is already in the field.
“Strong communication is essential when field issues arise, which is why choosing the right fabrication partner matters so much,” says Paul Daniels, chief brand ambassador of Los Angeles-based Frameless Hardware Company. “Beyond supplying the IGU itself, the fabricator needs to understand how that unit interacts within the overall door or framing system and integrated hardware.”
Most unseen compatibility issues involve interactions among coatings, sealants, spacers and gas fills, notes Peter Styk, CX tech manager for Press Glass. For instance, a component may perform well on its own but behave differently when paired with another material or exposed to certain environmental conditions. These issues are challenging because they may not appear during initial fabrication or short-term testing but instead emerge years later.
That’s why prevention, testing and dialogue among fabricators and suppliers is important.
“The industry places strong emphasis on prevention, through internal laboratory testing and third-party validation, to minimize the likelihood of field issues,” says Styk. “These efforts are critical because once problems arise on a project, the costs, financial, operational and reputational, can increase for all parties involved.”
When issues do arise, they often reveal themselves early in the life cycle of the IGU, says Daniels. He explains that longer-term failures are more closely tied to installation and operational conditions rather than the materials themselves. Issues such as glass support, setting block placement, hardware compatibility and installation conditions can all influence long-term performance.
To prevent those longer-term failures, free-flowing communication necessitates faster and more accurate root cause analysis, supports corrective actions and helps prevent similar problems in the future.
Styk explains that, in practice, when a potential component-related issue is identified, fabricators and suppliers rely on responsive support, technical expertise and quick reaction times to diagnose and remedy problems. This collaborative problem-solving network allows officials to determine whether the issue stems from material selection, fabrication practices or installation conditions.
Ultimately, the best partnerships are built long before a warranty claim happens, says Daniels.
Division of Responsibility
When an IGU underperforms or fails, who is responsible?
According to Styk, responsibility lies with the warrantor, often the IG fabricator. He explains that the fabricator provides the warranty on the finished IGU and is the first point of accountability from the customer’s perspective.
“However, determining the root cause of a failure often requires a deeper technical evaluation,” he adds. “This analysis is supported by full traceability of each individual component. If a specific component, such as a spacer, sealant or coating, is found to be the source of the issue, the fabricator will typically engage the supplier for support and potential shared responsibility.”
Losee says that should an IG underperform, a thorough investigation will probe the whole process, from design to field problems, including:
- Approved IGU make-up
- Coating position and edge deletion
- Spacer and sealant design
- Gas-fill or cavity configuration
- Production and quality-control records
- Component batch documentation
- Transport and lifting history
- Installation tolerances
- Field exposure and support conditions
Daniels explains that the audit usually begins with the building owner or end user reporting the issue to the installer, who then works with the manufacturer. From there, the investigation focuses on identifying the source of the failure.
“For example, with a thermal entrance door, the issue could stem from the IGU itself, the way the glass was integrated into the framing system, installation conditions or field handling,” says Daniels. “Performance failures such as fogging, seal failure or water infiltration require the door manufacturer and glass fabricator to evaluate their respective components and warranties.”
Fortunately, IG component-to-component compatibility issues are rare. Styk says this is due to extensive qualification, daily quality control and standardized testing before components are incorporated into the finished product.
Hidden Compatibility Issues
That need for traceability becomes important when problems are not immediately visible. While most IG component combinations are vetted before production, some risks only emerge after materials interact over time in the field.
Losee notes that most hidden risks are usually at the IGU edge, where moisture barriers, gas retention, adhesion and structural stability meet. However, performance also includes long-term optical quality. Losee underscores several potential issues, including:
- Coating-to-sealant adhesion and inconsistent edge deletion
- Spacer geometry that does not match the actual load case
- Wrong structural silicone sealant bite design
- Sealant compatibility with interlayers or coatings
- Anisotropies and the “rainbow effect” that often plague standard tempered glass
According to Styk, hidden compatibility issues are likely to emerge at the interface between the finished IGU and the glazing system in the field, such as interactions with setting blocks, shims, sealants, caulks and structural silicone used during installation.
That’s because the materials often are not tested as a complete system under long-term conditions.
“A well-known example is structural glazing applications, where polyvinyl butyral interlayer edges may come into direct contact with silicone sealants,” explains Styk. “Without proper system design or material use, this can lead to compatibility concerns over time. That said, most glazing contractors today have significant experience and typically rely on pre-testing, mock-ups, and supplier guidance to mitigate these risks. In many cases, proven solutions are already established before installation begins.”
Rethinking IG Systems
As performance demands rise, industry experts are rethinking which parts of the IG system, materials, design assumptions or fabrication processes most need to evolve first and why. USGlass magazine asked several glass industry officials for their thoughts.
Derek Losee, sales manager at sedak
I would redesign the process first. The industry still tends to specify IGUs as a set of separate components: glass, coating, spacer, sealant, gas fill, interlayer and frame system. That can work for standard units, but it is not sufficient for today’s oversized and highly engineered façade glass.
Large-format IGUs should be defined from day one as a complete performance system. That means visual quality, thermal performance, structural behavior, fabrication limits, transport, installation, edge design, long-term durability and maintenance all need to be considered together.
This is especially important in the United States market, where projects often combine ambitious architecture, high-performance envelope requirements, long logistics chains and demanding field conditions. For an IGU that may be 50 or 60 feet long, the question is not only “Which component is best?” The better question is: “Which complete build-up is right for this specific building, climate, geometry and installation method?”
Peter Styk, CX tech manager at Press Glass
If I had to prioritize one area for redesign, it would be the excessive variety of glass types currently available on the market. Today, the industry offers a broad range of tints, coatings and variations across multiple suppliers. While this provides flexibility, it also drives complexity far beyond what is truly necessary.
This level of variation often leads to inefficiencies in production — lower yield, higher scrap rates and increased glass waste. From a sustainability standpoint, it also contributes to a larger carbon footprint across the supply chain. Rationalizing and consolidating glass options into a more standardized, optimized portfolio would improve manufacturing efficiency and support more sustainable practices across the industry.
Joshua Huff is the senior editor of USGlass magazine. Email him at jhuff@glass.com and connect with him on LinkedIn.